Detailed design and works supervision
Advanced agrivoltaic plant on single-axis trackers, followed from detailed design through to construction.
The 2.4 MW plant on single-axis trackers, with configurations of twenty-eight and fourteen panels per tracker, falls under PNRR Mission 2 Component 2 Investment 1.1. The layout organises the site with internal roads, vehicle and pedestrian access, a perimeter mitigation strip, a corridor to the adjacent land and an area reserved for livestock, confirming the coexistence of power generation and animal farming.
Services were delivered in two phases: first the detailed design, with yield recalculation in PVsyst, structural calculations and details for cabins and civil works, and a lighting report; then works supervision and safety coordination during construction.
For construction, the seismic filing was made with the Tuscany Region; in August 2025 twelve pull-out tests were carried out on the supports and assembly began in November. The site was followed with a works log, weekly reports and acceptance testing of the tracker system with bolt certifications and steel tests.

Project data
Services delivered
Other projects
29.4 MW ridge wind farm, connected to the 132 kV transmission grid.
> project sheet
Design of a wind farm made up of 21 turbines and the associated connection works.
> project sheet
Construction and operation of a photovoltaic-agrivoltaic plant with a DC capacity of 49.38 MW.