Safety coordination and works supervision
Renewal of the railway track, internal roads and utility networks of a port logistics terminal in operation.
The works renew the track of a railway facility inside a port terminal connected to the national network: 60E1 rails on prestressed concrete sleepers, turnouts and crossings with V/50, V/75 and V/100 geometries. They also restore the internal roads used for container handling and upgrade the power and lighting networks.
The concession covers 125,870 m², served by thirteen gates with openings from 4.50 to 7.00 m. The safety and coordination plan sets the works over 180 days in an area classified at major accident hazard under the Seveso directive, with documented interfaces with four third-party owners and operators.
The works amounted to €2,100,000, plus €320,000 of variations. Works supervision was carried out in a non-interruptible environment, with digital accounting and GPS surveys.

Project data
Services delivered
Other projects
Detailed design of the priority eastern functional section, from the Tuscan border to Sarzana.
> project sheet
EIA of the feasibility design for a new bridge over the Arno and the connecting road.
> project sheet
Preliminary environmental study for the EIA screening procedure and detailed design of the soil bioengineering works.
> project sheetContact